    The Rundown

    Residents of Chadron, Nebraska, enjoyed using an outdoor pool during the summer months. When an indoor pool at Chadron State College needed replacement, the college and the city joined forces to build a modern indoor pool that would be open to all.

    Feature Details

    • 162 ft x 170 ft (27,540 sq ft)
    • Hot dip galvanized rigid steel frames
    • Flame-retardant fabric customized with tan, white and custom blue wave design
    • 36-inch overhangs with icebreakers and gutters in door locations
    • R-30 insulation with thermal break and 12 oz. fabric interior liner
    • 30 psf ground snow load, 90 mph wind speed, wind exposure C, seismic zone A
    • Legacy crews installed the building over an existing pool and structure and provided wrapped openings for doors, windows, HVAC and aquatic equipment
    Download Case Study

    Industry

    Sports & Recreation

    Size

    27,540 sq ft

    Location

    Chadron, NE

    Year

    2016

    Testimonials

    We had a great working relationship with Legacy

    A lot of the temporary structures in the region are fabric structures, so we mainly looked at those types of buildings. Due to the overall project timeline, the buildings had to be constructed in the dead of winter. We had a great working relationship with Legacy throughout the entire process. They supply a very high quality fabric structure, and we're certainly pleased with what we've seen from the buildings thus far.

    John Lehman BBE Hydro Constructors

    The building allowed us to get everything we wanted for the price we could afford.

    We are really happy with everything it’s provided for our community, including the lifestyle changes. We attracted 30 new kids to our school, which is really big for our town. And we feel that building is one of the main reasons for it. The building allowed us to get everything we wanted for the price we could afford.

    Kristen Milne Fox Creek

    Legacy was very easy to work with.

    The old buildings used tubular steel, and no matter what you do, the salt gets inside the tubes and corrodes them. They came out here with their crew, rented all their equipment, and erected the buildings in three weeks flat – a week ahead of schedule. It's a stand-up company.

    Theo Gatsonis CM & Sons